A material resource is a physical resource used to perform work orders.
It is associated with a team and is characterized by:
Its availability (or non-availability) are filled in via its calendar; see Material resources calendar and Material resources [Calendar].
Material resource timetable
If a piece of linked equipment is filled in for a material resource, the calendar for this equipment is used as the calendar for the material resource.
If the linked equipment is deleted or there is no equipment linked to the resource, the calendar for the material resource is that of the material resource itself.
Based on the calendar, the material resource's schedule will be built according to the assignment of the resource to work orders:
Subsequently, the time spent on various tasks will be completed in the work order reports, see Work orders [Material resources].
Material resource statuses
Status management enables you to track material resources, even after cancellation.
To change a material's resource's status, see Changing the status of an element.
Material resource schedule
Scheduling of resources