In this form you specify the settings for creating a project from:
Any work order hierarchy will then be created.
Source
You must fill in either the project or the project template.
- Project to duplicate: The project is created from an existing project. The full hierarchy of work orders is copied, in the same way as for copying work orders.
- Project template: The project is created from the Project template.
Initialization
- Start date: Start of the project and work orders. The end date is deduced from the duration of the project template or the original project.
- Status: Status of the project and the work orders created.
- Copy technicians: Method of copying resource lines on work orders (retaining the technician or only the discipline and the team).
Equipment
- Copy equipment: If this box is checked, the project equipment is deduced from the project template or the original project. Uncheck this box to assign different equipment to the project.
- Equipment: Same principle as for work orders.