Once preventive maintenance plans have been defined, it will be possible to trigger preventive operations.
Launching work order plans consists in creating preventive work orders according to the triggering conditions defined in the Work order plan.
Launching a work order plan is broken down into 4 steps:
Construction of the list
The list of work orders is built in the following way:
→ Case in which the "Trigger until" criterion is filled in on the [Search] tab: Trigger date <= indicated date.
→ Case in which the "Trigger until" criterion is not filled in: Trigger date <= current date + trigger horizon.
Preventive work orders created at the time of an earlier launch are no longer offered.
Launching of work order plans
Prerequisites:
Procedure:
Asynchronous processing: work order plans can be launched in manual mode (when very large) asynchronously so as not to block users.
As default, the threshold (expressed as a number of work orders to be generated) beyond which the asynchronous mode is triggered is 100work orders.
You can change this threshold in the System configuration [System] module, HMI section , asyncWoThreshold setting.
If you want the launching of work order plans to be preferentially asynchronous regardless of the number of work orders to be generated, this asyncWoThreshold setting should be set to the value 0.
If the user chooses to launch their work order plans manually (in asynchronous mode), a message is displayed indicating that the generation is being processed and that a memo will be sent when it is complete.