Planning [Macroplanning]
Work > Work order planning > Planning: Forms > Planning [Macroplanning]

In this form you view the GANTT work order chart and, by simply dragging with the mouse, you can:

An estimate of the daily workload is also displayed.

To ensure the consistency of the displayed data, changes are saved with each change of a tab or form.

To customize the display of bars on the GANTThart, see Configuring bar colors.

 

Display settings

 

Calendar

 

List of work orders

When the work order is selected, its dates and those of linked work orders are highlighted.

 

Chart

All work orders on the list are taken into account, including any appearing on another page.

 

Example of workload calculation:

Work order A runs from 2 to 3 April and has a workload of 10 hours, which is an average of five hours per day.
Work order B runs from 1 to 5 April and has a workload of 20 hours, which is an average of four hours per day.

→ The workload on 1 April is four hours, that of 2 April nine hours, that of 3 April nine hours, that of 4 April four hours, etc.