The scheduling allows for graphical handling and interactions to facilitate resource management.

Interactions

Basket

Creating a scheduled activity by graphic movement

You can graphically schedule user activities with basket work orders via drag & drop:

When an activity is created in the schedule, a resource line is created with the specific resource, a date and a period.

However, if there is an unscheduled resource line on the affected work order and the information of which may correspond to the activity created, the system then takes the resource line into account and changes it instead of adding a line. The activity information generated from the schedule is reconciled according to the following priorities:

  1. Same resource code?
  2. Same team and discipline?
  3. Same discipline?
  4. Same team?
  5. Resource line with only one time (which is then taken for the initialization of the activity on its creation)?

The consistency between the scheduled resources (technician/material resource) initialized on a work order and the resources (technician/material resource) that are actually assigned to that work order can be checked through the scheduling of resources.

The control level can be configured globally via the module settings as well as individually via the communication settings.

 

Highlighting of activities

You can view the activities over the displayed period in the scheduling of a specific work order. Simply select a work order tile.
All the work order activities in the schedule will be highlighted. The rest of the activities will be set back at the display level.

To deselect a tile, simply press Ctrl + mouse click on the selected work order.

 

Pre-initialized activity creation directly in the schedule

You can quickly create several activities directly in the scheduling for a work order.

You can use the shortcuts Ctrl+C (copy) and CTRL+V (paste) to duplicate the activity in the same work order even faster.

Schedule

Graphic handling

When you are on the graphical part of the schedule, you can graphically move the activities on the same line or a different line. However, the resource type must remain the same. This handling will result in a change to the work order's scheduled resource line.

When the user moves a work order tile or an existing activity on the scheduling part, a graphical help display is superimposed.
The schedule automatically greys out the days that are not included in the work order time frame (excluding the start/end date). However, it is not forbidden to create an activity on a date outside the time frame specified for the work order.

When the action is finished, this layer disappears.

 

You can also use the mouse to select several columns of a resource, which will result in the initialization of an activity. When the mouse button is released, a pop-up window is displayed to initialize the activity in order to save the desired activity.

 

Ephemeral system messages may appear on the right side of the screen to confirm actions performed using keyboard shortcuts or the configuration application.

 

Details of activity

When you double-click on a part of the schedule, a pop-up for creating an activity is displayed to fill in and save this new activity.

Double-clicking on an activity opens the activity detail pop-up.

 

Keyboard shortcuts

Keyboard shortcuts allow faster actions in the browsing and handling of scheduling items: