Synchronization links between work orders are taken into account in work order scheduling: if one of the work orders is shifted in the macroplanning, the linked work orders will be shifted by the same amount.
Example:
WORKORDER1 is scheduled from 3 April to 5 April and WORKORDER2 from 6 April to 8 April.
WORKORDER1 and WORKORDER2 are linked by a "Synchronized dates" link.
- In the macroplanning, I drag WORKORDER1 to delay it by two days.
→ WORKORDER2 will also be delayed by two days.- WORKORDER1 will then be scheduled from 5 to 7 April and WORKORDER2 from 8 to 10 April.