CARL Source offers you different levels of controls for each budget and Cost center .
Amount controls
CARL Source offers you different levels of controls that may differ according to the budgets and Cost centers.
Controls are performed at the time of commitment, that is, at the time of validation.
Example:
For year 2007, the total allowances of cost center C1 came to €10,000.
As of 30 September (three quarters of the year having passed), the total committed amount is €6,500 and the total incurred amount is €2,000.I validate a work order allocated to C1, the planned amount of which is €500.
The total allowances = €10,000 - Total allowances prorated to the period = €7,500 (i.e., 10000 × 3/4)
Total expenses = €9,000
Balance = €1,000 (10%) - Balance prorated to the period = <0→ There is no overall overrun, but an anticipated overrun. I will therefore be able to validate my work order.
However, I will not be able to validate a work order for €2,000 allocated to C1 if the control for C1 is "Prohibition if overrun."
Date controls
To prevent account statuses from changing long after the end of the month due to late entries, you can limit the number of days of back-dating to certain profiles.
Example:
The date is 20 April and my profile authorizes 10 days of back-dating.
→ I can enter a labor dated 10 April, but I cannot enter a labor dated 9 April.
The same will be true for an item receipt, an inventory movement, a measurement reading, and a validated contract period start date.