Work order plan with various action frequencies
Priority
Triggering
Action
1 Calendar: Every 12 months Complete overhaul 2 Calendar: Every 3 months Routine overhaul 3 Measurement: Every 1000 hours Inspection and adjustment 3 Calendar: Every month Inspection and adjustment Inspection and adjustment depend on 2 triggers having the same priority: the first one to occur will inhibit the other.
Fire protection inspection plan for a facility open to the public
Priority
Triggering
Action
Point
0 Calendar: Every 12 months Annual inspection of fire fighting equipment Bat721 0 Calendar: Every 12 months Inspection of automatic fire detectors Bat721 0 Calendar: Every 12 months Inspection of fixed CO2 extinguishers Bat721 0 Calendar: Every 6 months Inspection of portable extinguishers Bat721 0 Calendar: Every 12 months Inspection of automatic fire-stop devices Bat721 0 Calendar: Every 6 months Inspection of automatic water extinguishers Bat721 If this plan covers several buildings, determine a work order plan template that will be triggered for each building in question.
Work order plan of a given vehicle
In this case a plan per vehicle will be established by copying a work order plan template for the car template.
Illustration of the exclusion of meters
Priority
Triggering
Action
3 Measurement: Every 15,000 km Oil change 2 Measurement: Every 30,000 km Oil change + transmission fluid change 1 Measurement: Every 45,000 km Oil change + transmission fluid change + axle fluid change A trigger with a priority of 2 is triggered "in place of" a trigger with a priority of 3 every other time.
"Inspection patrols" work order plan
This plan contains one trigger line per structure point concerned by the round:
Triggering
Action
Calendar: Every month
Inspection round
Work order plan according to the Tolerances of triggers
A few cases specifying the use of tolerances on work order plan triggers.
Prerequisites:
Case 1:
| Priority | Asset | Meter | Work order template | Triggering conditions | Horizon | Tolerance (days) | Tolerance (unit) | Next launch date | Next launch value |
|---|---|---|---|---|---|---|---|---|---|
| 1 | MAT-45762 | PWO-45762_01 | Once a year | 15 | 5 | NULL | 08/02/2020 | ||
| 2 | MAT-45762 | PWO-45762_02 | Every 6 months | 15 | NULL | NULL | 10/02/2020 |
In this case, the two triggers are offered.
The trigger cannot be inhibited because the next launch date is not in the interval from 07/02/2020 to 09/02/2020 corresponding to the next launch date with a level plus or minus the tolerance in Days of level 2.
For level 2 to be inhibited, its next launch date must not be less than 07/02/2020 and not be greater 09/02/2020.
Case 2:
| Priority | Asset | Meter | Work order template | Triggering conditions | Horizon | Tolerance (days) | Tolerance (unit) | Next launch date | Next launch value |
|---|---|---|---|---|---|---|---|---|---|
| 1 | MAT-45762 | PWO-45762_01 | Once a year | 15 | 5 | NULL | 08/02/2020 | ||
| 2 | MAT-45762 | CPT-45762 | PWO-45762_02 | Every 6 months or every 5,000 km | 15 | 2 | 700 km | 12/02/2020 | 20,000 km |
In this case, the two triggers are offered:
Case 3:
| Priority | Asset | Meter | Work order template | Triggering conditions | Horizon | Tolerance (days) | Tolerance (unit) | Next launch date | Next launch value |
|---|---|---|---|---|---|---|---|---|---|
| 1 | MAT-45762 | CPT-45762 | PWO-45762_01 | Every year or every 10,000 km | 15 | 5 | NULL | 08/02/2020 | 20,000 km |
| 2 | MAT-45762 | CPT-45762 | PWO-45762_02 | Every 6 months or every 5,000 km | 15 | 2 | 500 km | 12/02/2020 | 20,000 km |
In this case, the two triggers are offered:
The delta of the extrapolated values between level 1 and 2 is 600 km and as this value is higher than the tolerance in units of level 2, level 2 is triggered.
Since for level 2 at least one of the trigger conditions (Calendar/meter) is fulfilled, it is triggered.
For level 2 to be inhibited, the minimum tolerance in units must be 600 km.
Case 4:
| Priority | Asset | Meter | Work order template | Triggering conditions | Horizon | Tolerance (days) | Tolerance (unit) | Next launch date | Next launch value |
|---|---|---|---|---|---|---|---|---|---|
| 1 | MAT-45762 | CPT-45762 | PWO-45762_01 | Every 10,000 km | 15 | 5 | NULL | 11,200 km | |
| 2 | MAT-45762 | CPT-45762 | PWO-45762_02 | Every 5,000 km | 15 | 2 | NULL | 11,800 km |
In this case, the two triggers are offered:
The delta of the extrapolated values between level 1 and 2 is 600 km or 4 days, this value being higher than the tolerance in days of level 2, then level 2 is triggered.
Since for level 2 at least one of the trigger conditions (Calendar/meter) is fulfilled, it is triggered.
For level 2 to be inhibited, the minimum tolerance in days must be 4.